Sir, what is the status of doubling of Manmad-Ahmednagar section of Central Railway?/ has any work started in this section?
2 Public Posts - Sun Oct 04, 2020
3 Public Posts - Sun Apr 11, 2021
2 Public Posts - Mon Apr 12, 2021
Hello.No work between Daund and Kashti.Good progress of Earth work between Srigonda road and Ranjangaon road.No progress in work between Rangaon to Vilad. Progress of Earth work between Vilad and Belapur. No progress in work between Belapur and Kopargaon.Nearly 80 %earthwork completed.Bridge construction over Godavari not started as yet.As per estimates, it may take more 5 years to complete ie 2026-27.
1 Public Posts - Sat Dec 18, 2021