Feb 28 2020 (12:45) 18048/Vasco-da-Gama - Shalimar Amaravati Express | UBL/SSS Hubballi Junction (Hubli) (8 PFs)
GntGtl~
GntGtl~ 134 blog postsRSA - Rake Sharing
NO RSA . 3 ( 2 ICF + 1 Uthkrist ) Rakes. PM - PDPK
GTL to Londa doubling is completed and it can run with e-loco till GTL. Change it as SF with speed up to reach VSG by 11 am, so that the same rake will return at 2 PM. with this 3 rakes they can run as daily.
NO RSA . 3 ( 2 ICF + 1 Uthkrist ) Rakes. PM - PDPK
GTL to Londa doubling is completed and it can run with e-loco till GTL. Change it as SF with speed up to reach VSG by 11 am, so that the same rake will return at 2 PM. with this 3 rakes they can run as daily.
They need to do secondary maintainance as the route is 2100km atleast 8hrs turnaround time is required. Check the same and reply as it has 24 hrs at HWH for PM
PRASANTHI from BBS to SBC will returning at SBC with in 1 hour time, the SM is rake sweeping and watering done at PF.
They can have RSA with a hwh to Puri express.