Railway Electrification is making significant progress even during Corona pandemic. CRS inspection of RE work of Anola-Bareli section of 27.5 RKM in the territory of NR completed on 14.09.2020.With this, total electrification completed by CORE in 2020-21 stands 423 RKM.
Source :- click here
Source :- click here
14 Posts
Now CHD Jn to ALG jn is left .isse section ka electrification hote hi yeh 3 train ko e loco mil jyega agle saal
Rishikesh Bandikui passenger
Bareilly Bandikui passenger
Dehradun link express
Rishikesh Bandikui passenger
Bareilly Bandikui passenger
Dehradun link express