Yelahanka - Devanahalli Electrification
AC Overhead Traction Wires To Be Energized On Or After 20.01.21
Posted thru Follow my Trip
AC Overhead Traction Wires To Be Energized On Or After 20.01.21
Posted thru Follow my Trip
1 Posts
What the hell? They told electrification will be complete by March 2021?
Bigger question is, when did the work even start? The Atlas shows it still being an unelectrified single line.
Electrification around SBC Is going at very Fast Pace. Don't know about YNK. But TK Section Saw ohe poles stacked all along some 25-30 days back
The only route hardly anyone has information about w.r t electrification is the YNK-BWT section. I'm surprised because there were no poles or pits seen in pics of the airport halt station (which is on the route to DHL)