Search Forum
Blog Entry# 4872361
Posted: Feb 10 2021 (08:21)
6 Responses
Last Response: Feb 14 2021 (21:40)
6 Responses
Last Response: Feb 14 2021 (21:40)
My guess is Bgp-Tekani electrification CRS on 17th feb(update:deferred to 23-25 feb). Banka side wiring shayad pending hai.
Update: bgp-barahat electrification is complete as per another report. Dumka-rph complete, crs by 24th feb
Update: bgp-barahat electrification is complete as per another report. Dumka-rph complete, crs by 24th feb
1 Posts
Rph to Dumka wiring already completed 15days ago....... other technical work like connection, battery work,is under process at good speed ....hope CRS can be done by 24feb
Along with BGP-tekni section
Along with BGP-tekni section
After electrification,mayurakshi fast passenger which run on e-loco may be start,with new time table from Dumka to Howrah