Ara junction ki koi latest update about its pitline and new platform..?
Hmmn..sick line pit line and platform 4 almost completed.. digital wall construction work on station facade, rwnnovation of circulating area on PF 1 side, new circulating area on 4 number side and another 3 metre wide FOB at howrah end is going on and expected to complete by june 2021. Shifting of goods yard to kulharia and construction of 2 pfs 1A and 1B at that place along with yard at delhi end is in process and is expected to complete by december 2021.
40 bed running room's construction is going on out of which a 6 bed running room is ready for now..