#Highlights of the Journey :
1.Fabricated beams installed for girders on the bridges
2.Good Progress of line doubling of left side and slow at right side
...
more...
#Highlights of the Journey :
1.Fabricated beams installed for girders on the bridges
2.Good Progress of line doubling of left side and slow at right side
...