DRUCC Members proposed to Guntur station yard remodeling project should be included in your Guntur - Guntakal doubling project.Present only 1 and 4 Platforms are 24 Coaches length Platforms in GNT JN. Another all Platforms are 16-20 length PF's only. If the Railway Board approves the proposal, all the platforms at Guntur station will be increased 24 coaches length and the constructed new 8th PF with 2 new stable lines.I hope the Railway Board approves this proposal
4 Public Posts - Fri Jun 18, 2021
Pendukallu Gooty project is not part of Guntur-Guntakal doubling work. Proposal has been sent for its doubling but as of now no idea on its fate
GTL bypass is added in Guntakal -Maddikera doubling work.
Also, linking of all lines in Guntakal station will be taken up as part of Guntur-Guntakal doubling work.
As per RTI reply, GTL bypass, linking of...
more...
GTL bypass is added in Guntakal -Maddikera doubling work.
Also, linking of all lines in Guntakal station will be taken up as part of Guntur-Guntakal doubling work.
As per RTI reply, GTL bypass, linking of...