Blog Entry# 5038077
Posted: Aug 10 2021 (11:35)

1 Responses
Last Response: Aug 30 2021 (21:40)
General Travel
25910 views
0

Aug 10 2021 (11:35)   52963/Dr. Ambedkar Nagar - Omkareshwar Road MG Passenger (UnReserved) | DADN/Dr. Ambedkar Nagar (Mhow) (3 PFs)
SonOfGalaxy
SonOfGalaxy   179 blog posts
Entry# 5038077            Tags   Past Edits
Update on Mhow Sanawad GC Project:


Total length - 472.64 km + 22.96 km ( Through material modification for Fatehabad-Chandravatiganj- Ujjain). Western railway- 298.64 km+ 22.96 km South central railway-174.00 km Railway wise progress is as under:- Western Railway :- Sections Commissioned-
(i)
...
more...
Dhoswas- Ratlam- Indore-Rau-Mhow– 147.70 KM (ii) Nimarkhedi- Mathela - 45.61 Km.
(iii) Sanawad-Nimarkhedi (11.6 Km)-CRS inspection done on 31.03.2021.
(iv) Fathabad-Ujjain (22.96 Km) –CRS inspection done on 11.02.2021.


Work in progress:-
i) Khandwa Bye Pass cabin to Khandwa (5.00 Km) –Tender for balance work awarded. Work is under progress.
ii) Rau-Mhow doubling (9.50 km ) – Tendering work in progress.


Mhow- Sanawad (84.65 Km ) : Detailed estimate sanctioned by Railway Board vide letter No. 93/W-I/GC/W/12/RTM-MHOW-Part-5 Dtd 05.07.19. Total 208.9 Hect. Forest land and 58.131 Hect.revenue land needs to be acquired. Demand note of Rs 34.12 Cr for forest land and Rs 14.98 Cr for revenue land is received. Land acquisition is under process.

1) Sanawad-Muktiyarbalwada- (26.10 km) The tender for Muktiya Balwada to Sanawad 26.10 Kms are to be done on EPC modules. Work is to be planned on EPC Module. Tender document under preparation.

2) Mhow- MuktiyaBalwada- (58.55 kms) Mhow- Mukhtiara section (58.65km), which will involve grade revision of 1:150 instead of 1:100 will be finalized after finalization of alignment and land acquisition 3) FLS quotation has been done and alignment work with 1 in 150 ruling gradient is in progress.

South Central Railway:-
1.Akola-Akot (43.50 Km) - commissioned.

2.Akot-Amalakhurd (77.43 Km) - Alignment is passing through Melghat tiger Reserve. Detailed Estimate sanctioned for carrying out GC on same alignment. But Forest and wild life clearances not received from Forest department. Work not started.

3. Amalkhurd - Khandwa (54.50 Km). - Work in progress. The track is passing through Reserved forest from Km 644.80 to km.619.80 between Gurhi-Amalakhurd stations. Revised on line application for diversion of forest land of 21.446 HA is submitted to Forest department on 26.05.2021. TDC : March 2023.

Fore more:
click here

Translate to English
Translate to Hindi

18284 views
0

Aug 30 2021 (21:40)guest
Re# 5038077-1              
Ye 2026 tak complete hoga...
Translate to English
Translate to Hindi
Scroll to Top
Scroll to Bottom
Go to Desktop site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy