Penukonda-Dharmavaram doubling. The works started. Land levelling is in progress from Penukonda side. You can observe the track partition and the levelled land. The pics 1&2 were not clear.pics 3&4 were taken on 15.02.2021 from road side. I didn't believed that the work is strted in last year itself. But today I confirm it the work is started.
3 Posts
Yes, it is for carrying out doubling of Penukonda-Devarapalli which is the left portion in Penukonda-Yelahanka doubling.
Unlike SCR, SWR will carryout most of the NI works before CRS inspection itself. Small NI works will be carried after CRS inspection