Mumbai Chennai Route: 26 Km Washimbe – Bhalwani CRS Inspection Done, Line Commissioned.
The 26.33-km Washimbe-Bhalwani section doubling is part of the Daund-Gulbarga doubling project. The doubling work includes the construction of 65 bridges (1 important, 2 major bridges), three new station buildings at Jeur, Pophalaj and Washimbe besides a new electronic interlocking system at four stations.
The 26.33-km Washimbe-Bhalwani section doubling is part of the Daund-Gulbarga doubling project. The doubling work includes the construction of 65 bridges (1 important, 2 major bridges), three new station buildings at Jeur, Pophalaj and Washimbe besides a new electronic interlocking system at four stations.