Nov 05 2021 (08:30) UBL/SSS Hubballi Junction (Hubli) (8 PFs)
GondiaSamnapurE~
GondiaSamnapurE~ 974 blog postsElectric locomotive trial completed between Hulkoti and Hubli (East) & OHE is charged to 25kV. Wiring work of SSS #Hubballi Station is in progress.
Source: click here
Source: click here
I think November 2021 End they should finish Hubli station yard Electrification..
IRI admin please update this info on map and change Hulikoti - Hubbali east cabin section from "Construction- Double line electrification " to "Double electric line".
UBL station wiring work is over and recently AC loco trial was conducted.