MywayRailway~ 715 blog postsThe First part of Doubling and Electrification Works From Gollapalli - Mahbubnagar from Gollapalli to Divitipalli is uploaded here The second part from Divitipalli to Mahbubnagar is uploaded 3 days ago
Are they constructing RUB at 4:17 or they are just shifting the crossing?
Good thing is that NI works at gollapalli, divitiappli , mbnr will be over soon so JCL-divitipalli commissioning will not be a big deal except bridge modification
Big question is will there be a single CRS for mbnr-divitipalli and jadcherla-gollapalli?
Good thing is that NI works at gollapalli, divitiappli , mbnr will be over soon so JCL-divitipalli commissioning will not be a big deal except bridge modification
Big question is will there be a single CRS for mbnr-divitipalli and jadcherla-gollapalli?
I guess your next video will be on krnt-dhne electrification :)
Still Jadcherla yard modification takes time to demolish 1st PF