TBM Vamika (S-1260) deployed by Afcons Infrastructure recorded its first breakthrough this evening by entering Dairy Circle station on Gottigere-Nagwara line of the Bangalore Metro Rail project. AFCONS is constructing this portion of 13.89km UG corridor.
Source- MetroRailToday
TBM Vamika (S-1260) deployed by Afcons Infrastructure recorded its first breakthrough this evening by entering Dairy Circle station on Gottigere-Nagwara line of the Bangalore Metro Rail project. AFCONS is constructing this portion of 13.89km UG corridor.
Source- MetroRailToday
47 Posts
Tin Factory Metro Station Construction Progress 🏗️🚧
Passenger Way Construction. Of Both Of Sides.
Lot More To Happen 🥲
Passenger Way Construction. Of Both Of Sides.
Lot More To Happen 🥲
Early Morning 🌅 Tin Factory
The Track Laying Work Has Already Started Inside Tin Factory Metro Station.
Also At Whitefield Side, Spotted Few Men On Track Laying.
The Track Laying Work Has Already Started Inside Tin Factory Metro Station.
Also At Whitefield Side, Spotted Few Men On Track Laying.
One More Steel Grider Will Be Deployed Tonight To Tin Factory Metro Station.
Assembly Has Been Done Today.
By This, Tin Factory Metro Station Will Connect Completely With Whitefield Route.
Assembly Has Been Done Today.
By This, Tin Factory Metro Station Will Connect Completely With Whitefield Route.
Bangalore Metro Update: Tender invited for design and manufacture of Standard Gauge Metro Cars for Bangalore Metro Rail project Phase 2, 2A and 2B
Trail run bw Baiyyapanahalli and whitefield scheduled from 25 oct.. Services expected to start on purple line till Whitefield from Mar 2023..