Finally Good New For #Konaseema railway line #SCR Sanction 296.51Crs For Railway line & Steel Griders For #Gowathmi Bridge.
In that news there is mention of only one bridge for Rs 300cr out of three bridges which are under construction. No word about land acquisition for 50km line status of land acquired and to be acquired , land will be acquired by state govt with their funds and give to IR or state govt has asked IR to pay for land acquisition, project cost sharing between state and central govt The total project cost is Rs 3000cr
Amalapuram district side ( EX East godavari district) land acquisition already completed land handover to SCR.
Long back SCR deposit 300 Crs For land acquisition to East godavari Collector
West godavari...
more...
Long back SCR deposit 300 Crs For land acquisition to East godavari Collector
West godavari...
more...
Look this news in 2021
Kotipali - NS new railway line required 900 Acres
East godavari side 800 Acres west godavari side 100 Acres.
As per this news East godavari side almost land acquisition is Completed
Kotipali - NS new railway line required 900 Acres
East godavari side 800 Acres west godavari side 100 Acres.
As per this news East godavari side almost land acquisition is Completed
509 acres required 289 acres is acquired, the rest 220 acres notification will be issued after joint survey by Oct 2021 as reported. Is the land acquired and are they any court cases pending ? Is the compensation amount disbursed and credited into land owners account then only land acquisition is complete. I got reply from one user in youtube that land acquisition is completed I'm EG Dt and WG is still pending. The newspapers only project news given by officials and not get into details completely and report.