Few Updates regarding PEH Yard remodelling through RTI.
Any local RF from DHN can confirm the following.
(1) Balance PF copping slabs and PF surface shuttering work, BFS, Sand filling dressing etc work
in...
more...
Any local RF from DHN can confirm the following.
(1) Balance PF copping slabs and PF surface shuttering work, BFS, Sand filling dressing etc work
in...
more...
Does 13301 has to get a loco reversal at Patherdih still ?
Is there any future plans to double the line from BJE to PEH?
Is there any future plans to double the line from BJE to PEH?
The Direct dispatch line to Sindri block hut is operational. Don't know LR is happening or not.. Any local RF can confirm the same..I am attaching the latest SIP Drawing of Pathardih for confirmation.
Is that line energized ? If that line is ready, why would 13301 would need to have a loco reversal at PEH.
When reintroduced, it wasn't having any reversal. I think a 5 or 7 month old YouTube vlog mentions a reversal at PEH.
Yes the line is energized.. .The connection was established in the month of april during the EI of Sindri block hut.