Blog Entry# 5748453
Posted: Jun 11 2023 (09:32)

24 Responses
Last Response: Jul 27 2023 (18:34)
Info Update
81292 views
16

★★
Jun 11 2023 (09:32)  
traintraveler21955
traintraveler21955   141 blog posts
Entry# 5748453               Past Edits
5 compliments
Useful Useful Useful Useful Useful
Edited Now (Previous update was of 6 June 2023)
Update as of 13 July 2023
Pune Miraj Doubling updates as of
● Pune to Shindawane (32 Km) FEDL

●
...
more...
Shindawane to Ambale (9 Km)
- Ground Leveling work is in final stage
- Two Viaducts work is completed out of 6 Viaducts
- 3 Viaducts foundation work is completed and pillars are in initial stage
- One Tunnel is in final stage

● Ambale to Nira (43 Km) FEDL

● Nira to Lonand (8 Km)
- Tracks are being laid
- Electrification work on 2nd Line going on

● Lonand to Adarki (17 Km) FEDL

● Adarki to Wathar (10 Km)
- Ground Leveling work is finished (remaining at Wathar outer only)
- New Down PF will come on Loop Line
- Tracks are being laid

● Wathar to Palsi (9 Km)
- Ground Leveling is done in some patches
- Ballast Mountains on some patches..not yet spreaded

● Palsi to Jarandeshwar (9 Km) FEDL

● Jarandeshwar to Satara (8 Km)
- No progess from Jarandeshwar side
- Some work visible from Satara side

● Satara to Koregaon (11 Km) FEDL

● Koregaon to Karad (48 Km)
- Leveling and Ballast work is in full swing till Masur
- Masur to Karad work at Average pace
- Work at Targaon,Rahimatpur,Masur and Shirravde at Good pace

● Karad to Shenoli (13 Km)
- Ground Leveling work finally started and 50% Progress

● Shenoli to Sangli (55 Km) FEDL

● Sangli to Miraj (7 Km)
- Ground Leveling work completed till Vishrambag outer(After Vishrambag station)
- Ground Leveling Work is in Final stage from Vishrambag Outer to Miraj Jn
- Level Crossing will be eliminated and Tracks will come soon

Double Line :- 167 Km
Under Construction:- 112 Km

Around 59% Double line
Around 41% Line Under construction

Translate to English
Translate to Hindi

7 Public Posts - Sun Jun 11, 2023

2 Public Posts - Mon Jun 12, 2023

8 Public Posts - Tue Jun 27, 2023

1 Public Posts - Sat Jul 01, 2023

1 Public Posts - Mon Jul 10, 2023

1 Public Posts - Tue Jul 11, 2023

15940 views
2

Jul 14 2023 (15:03)
traintraveler21955
traintraveler21955   141 blog posts
Re# 5748453-22              
1 compliments
Useful
Latest Update
13/7/23
Track Laying has started in Wathar Adarki section
Translate to English
Translate to Hindi

2 Public Posts - Wed Jul 26, 2023

1 Public Posts - Thu Jul 27, 2023
Scroll to Top
Scroll to Bottom
Go to Desktop site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy