Pune Edited Miraj Now Doubling (Previous updates update as was of 6/6/2023 6 June 2023)
Update as of 13 July 2023
Pune Miraj Doubling updates as of
- Two Viaducts work is completed out of 6 Viaducts
-2 or 3 Viaducts foundation work is completed and pillars are coming in up initial stage
- One Tunnel isalso in under final construction stage
-Bridge Tracks is are completed being just laid after Nira Station
-Ground Electrification Leveling is on started 2nd from Line end going of on Bridge and then From 1 km of that part
Ground Leveling is 100% completed
- tracks works also in progress
- Ground Leveling work isremaining finished in (remaining small at patches Wathar outer only)
- New Down PFof will Wathar come is on Demolished Loop Line
-Sleepers Tracks arrived are on being ground laid leveled part
-No Ground Leveling work finally started and 50% Progress
● Shenoli toNandre Sangli (42 (55 Km) FEDL
●Nandre Sangli to Miraj (20 (7 Km)
-Sleepers Ground and Leveling Tracks work are completed being till laid Vishrambag from outer(After Nandre Vishrambag to station) Madhavnagar
-Madhavnagar Ground Leveling Work is in Final stage from Vishrambag Outer to Sangli Miraj Outer(Before Jn Bridge) Ballast work done
-Sangli Level to Crossing Miraj start be eliminated and Tracks will come soon
Double Line :-154 167 Km
Under Construction:-125 112 Km
Around55% 59% Double line
Around45% 41% Line Under construction
Jun 12 2023 (13:03)
Groundleveling Leveling is in 100% Final completed stage till Lonand Outer
-Ballast tracks arrived works at also some in patches progress
will be spreaded soon
- Ground Leveling work is remaining inprogress small patches
- Sleepers arrived on ground leveled part
- Masur to Karad work atlow Average pace
- Work at Targaon,Rahimatpur,Masur and Shirravde at Good pace
Around 45% Line Under construction
Jun 11 2023 (09:35)
Anon Post Signed and Approved by: 248735/ForeverRailfan^~
Update as of 13 July 2023
Pune Miraj Doubling updates as of
- Two Viaducts work is completed out of 6 Viaducts
-
- One Tunnel is
-
-
- Ground Leveling work is
- New Down PF
-
-
● Shenoli to
●
-
-
-
Double Line :-
Under Construction:-
Around
Around
Jun 12 2023 (13:03)
Ground
-
- Ground Leveling work is remaining in
- Sleepers arrived on ground leveled part
- Masur to Karad work at
- Work at Targaon,Rahimatpur,Masur and Shirravde at Good pace
Around 45% Line Under construction
Jun 11 2023 (09:35)
Anon Post Signed and Approved by: 248735/ForeverRailfan^~
5 compliments
Useful Useful Useful Useful Useful
Useful Useful Useful Useful Useful
Edited Now (Previous update was of 6 June 2023)
Update as of 13 July 2023
Pune Miraj Doubling updates as of
● Pune to Shindawane (32 Km) FEDL
●...
more...
Update as of 13 July 2023
Pune Miraj Doubling updates as of
● Pune to Shindawane (32 Km) FEDL
●...
more...
Shindawane to Ambale (9 Km)
- Ground Leveling work is in final stage
- Two Viaducts work is completed out of 6 Viaducts
- 3 Viaducts foundation work is completed and pillars are in initial stage
- One Tunnel is in final stage
● Ambale to Nira (43 Km) FEDL
● Nira to Lonand (8 Km)
- Tracks are being laid
- Electrification work on 2nd Line going on
● Lonand to Adarki (17 Km) FEDL
● Adarki to Wathar (10 Km)
- Ground Leveling work is finished (remaining at Wathar outer only)
- New Down PF will come on Loop Line
- Tracks are being laid
● Wathar to Palsi (9 Km)
- Ground Leveling is done in some patches
- Ballast Mountains on some patches..not yet spreaded
● Palsi to Jarandeshwar (9 Km) FEDL
● Jarandeshwar to Satara (8 Km)
- No progess from Jarandeshwar side
- Some work visible from Satara side
● Satara to Koregaon (11 Km) FEDL
● Koregaon to Karad (48 Km)
- Leveling and Ballast work is in full swing till Masur
- Masur to Karad work at Average pace
- Work at Targaon,Rahimatpur,Masur and Shirravde at Good pace
● Karad to Shenoli (13 Km)
- Ground Leveling work finally started and 50% Progress
● Shenoli to Sangli (55 Km) FEDL
● Sangli to Miraj (7 Km)
- Ground Leveling work completed till Vishrambag outer(After Vishrambag station)
- Ground Leveling Work is in Final stage from Vishrambag Outer to Miraj Jn
- Level Crossing will be eliminated and Tracks will come soon
Double Line :- 167 Km
Under Construction:- 112 Km
Around 59% Double line
Around 41% Line Under construction
- Ground Leveling work is in final stage
- Two Viaducts work is completed out of 6 Viaducts
- 3 Viaducts foundation work is completed and pillars are in initial stage
- One Tunnel is in final stage
● Ambale to Nira (43 Km) FEDL
● Nira to Lonand (8 Km)
- Tracks are being laid
- Electrification work on 2nd Line going on
● Lonand to Adarki (17 Km) FEDL
● Adarki to Wathar (10 Km)
- Ground Leveling work is finished (remaining at Wathar outer only)
- New Down PF will come on Loop Line
- Tracks are being laid
● Wathar to Palsi (9 Km)
- Ground Leveling is done in some patches
- Ballast Mountains on some patches..not yet spreaded
● Palsi to Jarandeshwar (9 Km) FEDL
● Jarandeshwar to Satara (8 Km)
- No progess from Jarandeshwar side
- Some work visible from Satara side
● Satara to Koregaon (11 Km) FEDL
● Koregaon to Karad (48 Km)
- Leveling and Ballast work is in full swing till Masur
- Masur to Karad work at Average pace
- Work at Targaon,Rahimatpur,Masur and Shirravde at Good pace
● Karad to Shenoli (13 Km)
- Ground Leveling work finally started and 50% Progress
● Shenoli to Sangli (55 Km) FEDL
● Sangli to Miraj (7 Km)
- Ground Leveling work completed till Vishrambag outer(After Vishrambag station)
- Ground Leveling Work is in Final stage from Vishrambag Outer to Miraj Jn
- Level Crossing will be eliminated and Tracks will come soon
Double Line :- 167 Km
Under Construction:- 112 Km
Around 59% Double line
Around 41% Line Under construction
please wait...Translate to English
Updated now (Last update was on June 6, 2023)
Latest update as of July 13, 2023
Pune Miraj Doubling updates:
● Pune to Shindawane (32 Km) FEDL
● Shindawane to Ambale (9 Km)
- Ground Leveling work is almost done
- 2 out of 6 viaducts are completed
- 3 viaducts' foundation work is done and pillars are in progress
- One tunnel is almost complete
● Ambale to Nira (43 Km) FEDL
● Nira to Lonand (8 Km)
- Tracks are being laid
- Electrification work for the 2nd line is ongoing
● Lonand to Adarki (17 Km) FEDL
● Adarki to Wathar (10 Km)
- Ground Leveling work is finished (except at Wathar outer)
- New down platform will be added on the loop line
- Tracks are being laid
● Wathar to Palsi (9 Km)
- Ground Leveling is done in some areas
- Ballast mountains are still not spread out in some areas
● Palsi to Jarandeshwar (9 Km) FEDL
...
Latest update as of July 13, 2023
Pune Miraj Doubling updates:
● Pune to Shindawane (32 Km) FEDL
● Shindawane to Ambale (9 Km)
- Ground Leveling work is almost done
- 2 out of 6 viaducts are completed
- 3 viaducts' foundation work is done and pillars are in progress
- One tunnel is almost complete
● Ambale to Nira (43 Km) FEDL
● Nira to Lonand (8 Km)
- Tracks are being laid
- Electrification work for the 2nd line is ongoing
● Lonand to Adarki (17 Km) FEDL
● Adarki to Wathar (10 Km)
- Ground Leveling work is finished (except at Wathar outer)
- New down platform will be added on the loop line
- Tracks are being laid
● Wathar to Palsi (9 Km)
- Ground Leveling is done in some areas
- Ballast mountains are still not spread out in some areas
● Palsi to Jarandeshwar (9 Km) FEDL
...
please wait...Translate to Hindi
Abhi toh update hua hai (pichhli update 6 June 2023 ko hui thi)
Update ab tak ka hai 13 July 2023 tak
Pune Miraj Doubling ke updates:
● Pune se Shindawane tak (32 Km) FEDL
● Shindawane se Ambale tak (9 Km)
- Ground Leveling ka kaam final stage mein hai
- 6 Viaducts mein se 2 viaducts ka kaam poora ho gaya hai
- 3 viaducts ki foundation ka kaam ho gaya hai aur pillars initial stage mein hain
- Ek tunnel final stage mein hai
● Ambale se Nira tak (43 Km) FEDL
● Nira se Lonand tak (8 Km)
- Tracks lag rahe hain
- 2nd line par electrification ka kaam chal raha hai
● Lonand se Adarki tak (17 Km) FEDL
● Adarki se Wathar tak (10 Km)
- Ground Leveling ka kaam ho chuka hai (Wathar outer mein abhi baaki hai)
- New Down PF Loop Line par banega
- Tracks lag rahe hain
● Wathar se Palsi tak (9 Km)
- Ground Leveling ka kaam kuchh patches mein ho chuka hai
- Kuchh patches mein Ballast Mountains abhi tak spread nahi huye hain
● Palsi se Jarandeshwar tak (9 Km) FEDL
● Jarandeshwar se Satara tak (8 Km)
- Jarandeshwar taraf se koi progress nahi hai
- Satara taraf se thoda kaam dikh raha hai
● Satara se Koregaon tak (11 Km) FEDL
● Koregaon se Karad tak (48 Km)
- Leveling aur Ballast ka kaam Masur tak full swing mein hai
- Masur se Karad tak average pace mein kaam chal raha hai
- Targaon, Rahimatpur, Masur aur Shirravde mein kaam achhe pace mein chal raha hai
● Karad se Shenoli tak (13 Km)
- Ground Leveling ka kaam ab finally shuru hua hai aur 50% progress hai
● Shenoli se Sangli tak (55 Km) FEDL
● Sangli se Miraj tak (7 Km)
- Ground Leveling ka kaam Vishrambag outer tak poora ho gaya hai (Vishrambag station ke baad)
- Ground Leveling ka kaam Vishrambag Outer se Miraj Jn tak final stage mein hai
- Level Crossing hataya jayega aur tracks jaldi aayenge
Double Line: 167 Km
Under Construction: 112 Km
Lagbhag 59% double line ban chuki hai
Lagbhag 41% line abhi construction mein hai
Update ab tak ka hai 13 July 2023 tak
Pune Miraj Doubling ke updates:
● Pune se Shindawane tak (32 Km) FEDL
● Shindawane se Ambale tak (9 Km)
- Ground Leveling ka kaam final stage mein hai
- 6 Viaducts mein se 2 viaducts ka kaam poora ho gaya hai
- 3 viaducts ki foundation ka kaam ho gaya hai aur pillars initial stage mein hain
- Ek tunnel final stage mein hai
● Ambale se Nira tak (43 Km) FEDL
● Nira se Lonand tak (8 Km)
- Tracks lag rahe hain
- 2nd line par electrification ka kaam chal raha hai
● Lonand se Adarki tak (17 Km) FEDL
● Adarki se Wathar tak (10 Km)
- Ground Leveling ka kaam ho chuka hai (Wathar outer mein abhi baaki hai)
- New Down PF Loop Line par banega
- Tracks lag rahe hain
● Wathar se Palsi tak (9 Km)
- Ground Leveling ka kaam kuchh patches mein ho chuka hai
- Kuchh patches mein Ballast Mountains abhi tak spread nahi huye hain
● Palsi se Jarandeshwar tak (9 Km) FEDL
● Jarandeshwar se Satara tak (8 Km)
- Jarandeshwar taraf se koi progress nahi hai
- Satara taraf se thoda kaam dikh raha hai
● Satara se Koregaon tak (11 Km) FEDL
● Koregaon se Karad tak (48 Km)
- Leveling aur Ballast ka kaam Masur tak full swing mein hai
- Masur se Karad tak average pace mein kaam chal raha hai
- Targaon, Rahimatpur, Masur aur Shirravde mein kaam achhe pace mein chal raha hai
● Karad se Shenoli tak (13 Km)
- Ground Leveling ka kaam ab finally shuru hua hai aur 50% progress hai
● Shenoli se Sangli tak (55 Km) FEDL
● Sangli se Miraj tak (7 Km)
- Ground Leveling ka kaam Vishrambag outer tak poora ho gaya hai (Vishrambag station ke baad)
- Ground Leveling ka kaam Vishrambag Outer se Miraj Jn tak final stage mein hai
- Level Crossing hataya jayega aur tracks jaldi aayenge
Double Line: 167 Km
Under Construction: 112 Km
Lagbhag 59% double line ban chuki hai
Lagbhag 41% line abhi construction mein hai
7 Public Posts - Sun Jun 11, 2023
2 Public Posts - Mon Jun 12, 2023
8 Public Posts - Tue Jun 27, 2023
1 Public Posts - Sat Jul 01, 2023
1 Public Posts - Mon Jul 10, 2023
1 Public Posts - Tue Jul 11, 2023
1 Public Posts - Fri Jul 14, 2023
2 Public Posts - Wed Jul 26, 2023