Kindly update the atlas..
Section - nimach - ratlam single electric line section from construction doubling as the doubling has been started from long time..
Photos have been attached after nimach..
Train...
more...
Kindly update the atlas..
Section - nimach - ratlam single electric line section from construction doubling as the doubling has been started from long time..
Photos have been attached after nimach..
Train...
more...
60 Posts
Indore ujjain double line
Barlai-LMNR CRS inspection planned 26.11.23
Nimach-Ratlam doubling CRS inspection planned on 31.12.23
RAU-DADN...
more...
Barlai-LMNR CRS inspection planned 26.11.23
Nimach-Ratlam doubling CRS inspection planned on 31.12.23
RAU-DADN...
more...
Physical progress : 58% (Bhuj-Naliiya)
TDC : 34.00 Km - Dec'23 (Deshalpur- Mothala halt)
: 37.49 Km - Jan'24 (Mothala halt- Naliya)
: 24.65 Km. - Sep-26 (Naliya - Vayor)
TDC : 34.00 Km - Dec'23 (Deshalpur- Mothala halt)
: 37.49 Km - Jan'24 (Mothala halt- Naliya)
: 24.65 Km. - Sep-26 (Naliya - Vayor)
Jora Alapur gwalior fully electrified railway line please update crs done