the new gtl bypass line is single line only...it's not FEDL...also maddikera - gtl FED line is under construction.
Bypass is single line ? But scr mentioned as twin single lines .
Maddikera GTL doubling not completed?
Maddikera GTL doubling not completed?
there won't be any doubling between mallappa gate and GTL.
Essentially, it can handle both up and down, similarly bypass can also so they are called as twin single lines
Essentially, it can handle both up and down, similarly bypass can also so they are called as twin single lines
Maddikera to mallappagate completed. Mallappagate to GTL two lines there. One is direct to guntakal (already existing line). Another is bypass line( newly laid). So there may not be doubling between mallappagate to Guntakal. Already they are looking for doubling of Guntakal west to mallappagate bypass lines