Anand - Godhara doubling work in progress
➡️ length is 78.80 Km,
➡️ Station 13 nos .
➡️ Project cost is 692.26 Cr.
...
more...
➡️ length is 78.80 Km,
➡️ Station 13 nos .
➡️ Project cost is 692.26 Cr.
...
more...
Physical Progress: 26%
TDC: Phase I: Anand - Ordi (16.5 Km) - Jan.'2024
: Ordi-Thasra (21.7 Km) - Feb.2024
: Phase II: Thasra – Timba Road (13.27 Km) - Dec'24
: Timba...
more...
TDC: Phase I: Anand - Ordi (16.5 Km) - Jan.'2024
: Ordi-Thasra (21.7 Km) - Feb.2024
: Phase II: Thasra – Timba Road (13.27 Km) - Dec'24
: Timba...
more...