Spotting
 Timeline
 Travel Tip
 Trip
 Race
 Social
 Greeting
 Poll
 Img
 PNR
 Pic
 Blog
 News
 Conf TL
 RF Club
 Convention
 Monitor
 Topic
 #
 Rating
 Correct
 Wrong
 Stamp
 PNR Ref
 PNR Req
 Blank PNRs
 HJ
 Vote
 Pred
 @
 FM Alert
 FM Approval
 Pvt

RailCal app

site support

आम लोग: "रेल फैनिंग आती नहीं". RailFans: "रेल फैनिंग जाती नहीं" - Md Asif

Search Forum
<<prev entry    next entry>>
Blog Entry# 5920926
Posted: Dec 23 2023 (21:11)

2 Responses
Last Response: Dec 23 2023 (21:14)
Info Update
24404 views
6

Dec 23 2023 (21:11)   WR/Wardha Junction (4 PFs)
Exynos9611~   13663 blog posts
Entry# 5920926            Tags   Past Edits
2 compliments
Useful Useful
#Admin #Moderator Source Cr X Handle

Kindly Update It (1/2)

#CRInfraUpdates
Today
...
more...
23/12/23, CR has successfully completed & commissioned 23.69 km new line section between Deoli-Kalamb section on Wardha-Nanded line.
CRS (Commissioner of Railway Safety) Shri. Manoj Arora inspected the new line sections & given it's safe certificate.
Speed trial of 125 kmph conducted successfully in newly opened line.

Chief Administrative Officer construction/Shri. Avanish Kumar Pandey & DRM/Nagpur Shri. Tushar Kant Pandey also conducted inspection of new line.
With this 23.69 km new line opening, CR has completed construction of 185.49 km of new lines/double line/3rd/4th lines in April-December 2023.

❇Wardha-Nanded New line (via Yavatmal-Pusad).
Nagpur div.
🔸Length- 284.65 km
🔸Overall Physical Progress- 47%
💰 Cost- ₹ 3445.48 Cr
💰 Expenditure till date- ₹ 1910.07 Crs.
🔸Funding pattern-
Railways- 60%
State govt- 40%
🔸Land acquisition completed- 1911/2138 Hectare (89%)
🔸Total stations- 26
🔸Completed stations- 4

✳Completed Section-
38.61 km.
Wardha-Kalamb.
✳In Progress Sections-
246.05 km
Kalamb-Nanded

🟢In Progress Works-
☑Earthwork- 87.54/201.14 Lcum (44%)
☑Formation- 40/284.60 km
☑Major Bridges- 32/80 completed
☑Minor Bridges- 50/320 completed
☑Road over bridge (ROB)- 43 In Progress
☑Road under bridges (RUB)- 19/52 completed
☑Station Buildings- 4/26
☑Tunnels- 6 in progress of total 8 km length
☑Track Linking- 40/284.60 km

🟠Completion of this new line will improve connectivity of Vidarbha & Marathwada region for Wardha, Yavatmal, Washim, Nanded districts.

🔘CR completed 185.50 km new line/doubling/3rd/4th line from April'23 to till date
🔘3887 Crs planned by CR in this year for new lines/doubling/3rd/4th line
🔘3006 Crs expenditure done till date (77%)

Translate to English
Translate to Hindi

8778 views
5

Dec 23 2023 (21:13)
Exynos9611~   13663 blog posts
Re# 5920926-1              
1 compliments
Useful
Today 23/12/23, CR successfully completed & commissioned 23.69 km new line section between Deoli-Kalamb section on Wardha-Nanded line.
Total 38.61 km of this Wardha-Nanded new line is commissioned till now. (2/2)
Translate to English
Translate to Hindi

1 Public Posts - Sat Dec 23, 2023
Scroll to Top
Scroll to Bottom
Go to Desktop site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy