Everyone knows if a train is running late, ONLY RailFans know WHY it is late

Search Forum
<<prev entry    next entry>>
Blog Entry# 6169293
Posted: Aug 26 (19:51)

2 Responses
Last Response: Aug 26 (20:19)
General Travel
18709 views
6

Aug 26 (19:51)   GMN/Goregaon (7 PFs)
Kumaon_Tiger^~
Kumaon_Tiger^~   42751 blog posts
Entry# 6169293            Tags  
1 compliments
Great
Project Name: Commissioning of 6th Line Between Goregaon and Kandivali Stations
Length: Approx. 4.5 km
Duration: 42 days (35 working days)
Start Date: Night of August 27/28, 2024

Project
...
more...
Overview:
· The 6th line will be laid east of the existing tracks from Goregaon to Malad (S) and from Malad (N) to Kandivali.
· At Malad station (MDD), due to space constraints, the 6th line will be laid on the west side, necessitating the shift of all five existing lines to the west through cut and connection.

All 5 cut connection blocks will operate on weekends on Saturday/Sunday.

Mega Block Schedule:
1. First Mega Block:
· Date: 31/01-09-2024
· Duration: 10 hours
· Impact: 150 suburban cancellations, 60 short terminations, 50-60 delays.

2. Second Mega Block:
· Date: 07/08-09-2024
· Duration: 10 hours
· Impact: 150 suburban cancellations, 60 short terminations, 50-60 delays

There will be no work from 11.09.2024 to 17.09.2024 due to Ganpati Festival.

3. Third Mega Block:
· Date: 21/22-09-2024
· Duration: 10 hours
· Impact: 180 suburban cancellations, 60 short terminations, 50-60 delays

4. Fourth Mega Block:
· Date: 28/29-09-2024
· Duration: 10 hours
· Impact: 200 suburban cancellations, 60 short terminations, 70 delays

NI work at GMN will Start from 29/30-09-2024 During GMN NI (for 5 Days)
· Impact: 90-95 Avg suburban cancellations, 70-75 avg short terminations, 110-120 avg delays.

5. Fifth Mega Block:
· Date: 05/06-10-2024
· Duration: 10 hours
· Impact: 100 suburban cancellations, 30 short terminations, 60-70 delays

Due to caution order on all lines, daily 20-22 long distance trains will be regulated by 15-20 minutes.
Along with this, from 28/29-09-2024, non-interlocking work will also be done on 5th line between Goregaon and Kandivali.
Due to this, trains running from Bandra Terminus will be regulated by 40-45 minutes.

Benefits:
· Decongestion of the 5th line between Goregaon and Borivali.
· Improved punctuality for trains originating and terminating at BDTS.
· Enhanced suburban train punctuality.
· Creation of additional train paths.

Source- DRM BCT X handle

Translate to English
Translate to Hindi

7068 views
0

Aug 26 (20:05)
YogiRaj^~
YogiRaj^~   1736 blog posts
Re# 6169293-1              
Kya tum DRM ho ? Nahi naa to yeh Spam hai #FM yeh Kumau vala spam kar raha hai take. Action 😂😂😂
Translate to English
Translate to Hindi

5131 views
1

Aug 26 (20:19)
Kumaon_Tiger^~
Kumaon_Tiger^~   42751 blog posts
Re# 6169293-2              
1 compliments
_/\_
Plz sir koi action mt lijiye. Ye Top secret info maine direct elon musk se baat krke X ke headquaters se leak krwai h.
Translate to English
Translate to Hindi
Scroll to Top
Scroll to Bottom
Go to Desktop site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy