#electrification @GKP.
.
Till BST from BBK fully completed. BST to KLD Ground work completed and some wire work done.
.
KLD to GKP : low speed of work very few area covered by...
more...
.
Till BST from BBK fully completed. BST to KLD Ground work completed and some wire work done.
.
KLD to GKP : low speed of work very few area covered by...
more...
23 Posts
It's great
Sahjanwa, just 17 km frm GKP, gettin fully electrified by July :)
Sahjanwa, just 17 km frm GKP, gettin fully electrified by July :)
Some info By our member Pulkit Goel:
.
Unwired Poles can be seen at BTT outer towards CPR. BTT-CC no poles. after CC, one line has been wired for long (atleast before march), only new thing i saw was that the othr line (GKP-CC) was having poles and all stations enroute has overhead catenary mast in place. so only wiring left on GKP-CC section. stations hav 1 or 2 lines wired and remaining 3 or 4 unwired. Note: stations on GKC-CC section have 5 lines instead of conventional 4 lines.
....
more...
.
Unwired Poles can be seen at BTT outer towards CPR. BTT-CC no poles. after CC, one line has been wired for long (atleast before march), only new thing i saw was that the othr line (GKP-CC) was having poles and all stations enroute has overhead catenary mast in place. so only wiring left on GKP-CC section. stations hav 1 or 2 lines wired and remaining 3 or 4 unwired. Note: stations on GKC-CC section have 5 lines instead of conventional 4 lines.
....
more...
5 lines instead on conventional 4 lines?
can you please elaboraet, i am lost in this respect
can you please elaboraet, i am lost in this respect
Latest Update by Pulkit Goel:
.
catenary at domingarh. sahjanwa was disappointing. after that wires ruled. stll work left in patches. dec 2013 is an ideal deadline. 05027 did gkp-bst in whooping 58 min. with a stop at kld. now leaving bst and attendant forcing me to go to my seat... bst unwired. work speed poor. beyond bst wired. work needs to speed up.
.
catenary at domingarh. sahjanwa was disappointing. after that wires ruled. stll work left in patches. dec 2013 is an ideal deadline. 05027 did gkp-bst in whooping 58 min. with a stop at kld. now leaving bst and attendant forcing me to go to my seat... bst unwired. work speed poor. beyond bst wired. work needs to speed up.