#Indorenews RTM-FTD Guage conversion is delayed due to early Monsoon.Now trains will start running from September.
RTM-INDB full sector ka gauge conversion kab pura hoga..? waiting since ages.. :-/
poor planning and estimates by railways, the plan was to complete by march. and 3 months for testing and other things, after 3 months also its not complete..the worst part is they not even learn from mistakes, now the plan for ftd-indb is to start from jan 2014, why cant they start early when they know their estimates are never correct and usually less than half of actual. just as the monsoon stops..like in sept/oct they should start work on ftd-indb.