Aug 10 2021 (14:22) 02715/Sachkhand Special (PT) | AWB/Aurangabad (5 PFs)
ssastronaut~
ssastronaut~ 920 blog posts#ElectrificationUpdate #Electrification #administrator #admin #moderator
Pole foundation work started on Manmad (Ankai)-Mudkhed section from Ankai end, as informed by loco pilot.
Finally, the electrification started on the only remaining section of NED division.
Pole foundation work started on Manmad (Ankai)-Mudkhed section from Ankai end, as informed by loco pilot.
Finally, the electrification started on the only remaining section of NED division.
6 Public Posts - Tue Aug 24, 2021
4 Public Posts - Wed Aug 25, 2021
1 Public Posts - Sun Aug 29, 2021
1 Public Posts - Tue Aug 31, 2021
13 Public Posts - Tue Aug 10, 2021
#ElectrificationUpdate #03March2020
DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
Last step completed successfully which is nothing but green signal from Commission of Railway Safety to run eloco on DAL/DaliGanj Junction - STP/Sitapur Junction section.
DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
Last step completed successfully which is nothing but green signal from Commission of Railway Safety to run eloco on DAL/DaliGanj Junction - STP/Sitapur Junction section.
1 Public Posts - Tue Mar 03, 2020
3 Public Posts - Wed Mar 04, 2020
1 Public Posts - Thu Mar 05, 2020
#ElectrificationUpdate #26February2020
DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
Finally CRS inspection completed successfully and maximum permissible speed (MPS) is expected as 110Km/hr.
Couple of snap's of CRS inspection held on 25Feb2020
PC :...
more...
DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
Finally CRS inspection completed successfully and maximum permissible speed (MPS) is expected as 110Km/hr.
Couple of snap's of CRS inspection held on 25Feb2020
PC :...
more...
2 Public Posts - Wed Feb 26, 2020
1 Public Posts - Mon Mar 02, 2020
2 Public Posts - Tue Mar 03, 2020
#ElectrificationUpdate #25February2020
DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
CRS inspection from DAL/DaliGanj Junction has started at 10:30AM with 10 coaches train which was hauled by GD WDM3A 14061R diesel loco. After departing from DAL/DaliGanj Junction CRS special train reached SD/Sidhauli where light snacks was arranged but team didn't had due to time constrain and moved to KMP/Kamlapur where lunch was served. After lunch inspection convoy moved towards STP/Sitapur Junction and reached around 05:30PM. After inspecting RE at STP/Sitapur Junction for around 1 hour inspection train departed STP/Sitapur Junction around 06:30PM for...
more...
DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
CRS inspection from DAL/DaliGanj Junction has started at 10:30AM with 10 coaches train which was hauled by GD WDM3A 14061R diesel loco. After departing from DAL/DaliGanj Junction CRS special train reached SD/Sidhauli where light snacks was arranged but team didn't had due to time constrain and moved to KMP/Kamlapur where lunch was served. After lunch inspection convoy moved towards STP/Sitapur Junction and reached around 05:30PM. After inspecting RE at STP/Sitapur Junction for around 1 hour inspection train departed STP/Sitapur Junction around 06:30PM for...
more...
2 Public Posts - Tue Feb 25, 2020
1 Public Posts - Wed Feb 26, 2020
Page# 21 Blog Entries next>>