Spotting
 Timeline
 Travel Tip
 Trip
 Race
 Social
 Greeting
 Poll
 Img
 PNR
 Pic
 Blog
 News
 Conf TL
 RF Club
 Convention
 Monitor
 Topic
 #
 Rating
 Correct
 Wrong
 Stamp
 PNR Ref
 PNR Req
 Blank PNRs
 HJ
 Vote
 Pred
 @
 FM Alert
 FM Approval
 Pvt

RailCal app

site support

For RailFans, the Journey itself is the Destination. - Sreerup Patranabis

Search Forum
Filters:
Page#    2 Blog Entries  
General Travel
3436 views
1

Jan 31 (22:46)  
traintraveler21955
traintraveler21955   141 blog posts
Entry# 5957774              
#PuneMirajDoublingProject
●SECTION : SATARA to MIRAJ●

● Satara to Koregaon (11 Km) FEDL

...
more...
Koregaon to Targaon (21 Km)
Work of Ground Leveling and Blanketing is Partially completed
Work is pending at some spots
Tracks are laid at Targaon Outer before station

●Targaon to Shirravde (18 Km)
Work is full swing in this stretch
Tracks Laying Work is almost completed and top ballasting Work is going on
Pole foundation on 2nd line is visible
Alignment is Left-Right-Left to reduce sharp curves
CRS can happen soon

●Shirravde to Shenoli (22 Km)
Ground leveling work is completed at most of places and Blanketing work is also going on
Some Minor Bridges work is pending
Ground leveling work is pending at few places
Ohe pole foundation pits can be visible in Karad to Shenoli section

● Shenoli to Miraj (62 Km) FEDL

Total Doubled Line= 73 Km
Under Doubling = 61 Km

Source :- YouTube channel:- KD Travel Studio
Attaching videos of the same to this post

Translate to English
Translate to Hindi

2 Public Posts - Wed Jan 31, 2024
General Travel
5580 views
4

Jan 25 (12:25)  
traintraveler21955
traintraveler21955   141 blog posts
Entry# 5951863               Past Edits
1 compliments
Useful
#PuneMirajDoublingProject
● SECTION : PUNE TO SATARA ●

● Pune to Shindawane (31KM) FEDL

...
more...
Shindawane to Ambale (10KM)
Shindawane Ghat Doubling
Bridge no 35/1 :- Pillar work completed,Span work remaining
Tunnel No 1(Dn Line) :- Boring completed,Ground leveling work inprogress
Bridge No 36/1 and 36/2 :- Fully Completed,Track Laying and Pole erection pending
Bridge no 37/1 :- Foundation work started
Bridge No 37/2 and 37/3 :- No Work
Bridge No 38/1 :- Pillar work completed, Span work remaining
Ground Leveling work is almost completed
Poles are erected at some patches
Partially bracketing is done from Shindawane outer to some distance so as partially wiring at some places

● Ambale to Wathar (78 KM) FEDL

● Wathar to Palsi (9 KM)
Ground Leveling work and pole foundation work is in progress
Ground leveling work yet to start at some points

● Palsi to Jarandeshwar (9 KM) FEDL

● Jarandeshwar to Satara (8 KM)
Subgrade Work,Rock Cutting work and Minor Bridges work in progress
Blanketing ballast has arrived at some points

Total Doubled Line :- 118 KM
Under Doubling :- 27 KM

Source :- YouTube channel : KD Travel Studio
Attaching Vdos of the same under this post

Translate to English
Translate to Hindi

2 Public Posts - Thu Jan 25, 2024
Page#    2 Blog Entries  

Scroll to Top
Scroll to Bottom
Go to Desktop site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy