Koregaon to Targaon (21 Km)
Work of Ground Leveling and Blanketing is Partially completed
Work is pending at some spots
Tracks are laid at Targaon Outer before station
●Targaon to Shirravde (18 Km)
Work is full swing in this stretch
Tracks Laying Work is almost completed and top ballasting Work is going on
Pole foundation on 2nd line is visible
Alignment is Left-Right-Left to reduce sharp curves
CRS can happen soon
●Shirravde to Shenoli (22 Km)
Ground leveling work is completed at most of places and Blanketing work is also going on
Some Minor Bridges work is pending
Ground leveling work is pending at few places
Ohe pole foundation pits can be visible in Karad to Shenoli section
● Shenoli to Miraj (62 Km) FEDL
Total Doubled Line= 73 Km
Under Doubling = 61 Km
Source :- YouTube channel:- KD Travel Studio
Attaching videos of the same to this post
Work of Ground Leveling and Blanketing is Partially completed
Work is pending at some spots
Tracks are laid at Targaon Outer before station
●Targaon to Shirravde (18 Km)
Work is full swing in this stretch
Tracks Laying Work is almost completed and top ballasting Work is going on
Pole foundation on 2nd line is visible
Alignment is Left-Right-Left to reduce sharp curves
CRS can happen soon
●Shirravde to Shenoli (22 Km)
Ground leveling work is completed at most of places and Blanketing work is also going on
Some Minor Bridges work is pending
Ground leveling work is pending at few places
Ohe pole foundation pits can be visible in Karad to Shenoli section
● Shenoli to Miraj (62 Km) FEDL
Total Doubled Line= 73 Km
Under Doubling = 61 Km
Source :- YouTube channel:- KD Travel Studio
Attaching videos of the same to this post
please wait...Translate to English
The Pune Miraj Doubling Project is underway. Here's an update on the progress:
- Satara to Koregaon (11 Km): Some work has been completed, but there are still pending spots. Tracks have been laid at Targaon Outer before the station.
- Koregaon to Targaon (21 Km): Ground leveling and blanketing work is partially completed. Some areas are still pending. Tracks laying work is almost done and top ballasting work is in progress. You can see the pole foundation on the second line. CRS (Commissioner of Railway Safety) approval can be expected soon.
- Targaon to Shirravde (18 Km): Work is in full swing in this stretch. Tracks laying work is almost completed, and top ballasting work is ongoing. The alignment has been set to reduce sharp curves. CRS approval can be expected soon.
- Shirravde to Shenoli (22 Km): Ground leveling work is completed at most places, and blanketing work is ongoing. Some minor bridge work is pending, and there are a few spots where ground leveling work is still pending. You can see OHE (Overhead Equipment) pole foundation pits in the Karad to Shenoli section.
- Shenoli to Miraj (62 Km): This section is under construction.
Total doubled line: 73 Km
Under doubling: 61 Km
Source: YouTube channel - KD Travel Studio. Videos are attached to this post.
please wait...Translate to Hindi
![](http://st.indiarailinfo.com/images/1.png)
Shindawane to Ambale (10KM)
Shindawane Ghat Doubling
Bridge no 35/1 :- Pillar work completed,Span work remaining
Tunnel No 1(Dn Line) :- Boring completed,Ground leveling work inprogress
Bridge No 36/1 and 36/2 :- Fully Completed,Track Laying and Pole erection pending
Bridge no 37/1 :- Foundation work started
Bridge No 37/2 and 37/3 :- No Work
Bridge No 38/1 :- Pillar work completed, Span work remaining
Ground Leveling work is almost completed
Poles are erected at some patches
Partially bracketing is done from Shindawane outer to some distance so as partially wiring at some places
● Ambale to Wathar (78 KM) FEDL
● Wathar to Palsi (9 KM)
Ground Leveling work and pole foundation work is in progress
Ground leveling work yet to start at some points
● Palsi to Jarandeshwar (9 KM) FEDL
● Jarandeshwar to Satara (8 KM)
Subgrade Work,Rock Cutting work and Minor Bridges work in progress
Blanketing ballast has arrived at some points
Total Doubled Line :- 118 KM
Under Doubling :- 27 KM
Source :- YouTube channel : KD Travel Studio
Attaching Vdos of the same under this post
Shindawane Ghat Doubling
Bridge no 35/1 :- Pillar work completed,Span work remaining
Tunnel No 1(Dn Line) :- Boring completed,Ground leveling work inprogress
Bridge No 36/1 and 36/2 :- Fully Completed,Track Laying and Pole erection pending
Bridge no 37/1 :- Foundation work started
Bridge No 37/2 and 37/3 :- No Work
Bridge No 38/1 :- Pillar work completed, Span work remaining
Ground Leveling work is almost completed
Poles are erected at some patches
Partially bracketing is done from Shindawane outer to some distance so as partially wiring at some places
● Ambale to Wathar (78 KM) FEDL
● Wathar to Palsi (9 KM)
Ground Leveling work and pole foundation work is in progress
Ground leveling work yet to start at some points
● Palsi to Jarandeshwar (9 KM) FEDL
● Jarandeshwar to Satara (8 KM)
Subgrade Work,Rock Cutting work and Minor Bridges work in progress
Blanketing ballast has arrived at some points
Total Doubled Line :- 118 KM
Under Doubling :- 27 KM
Source :- YouTube channel : KD Travel Studio
Attaching Vdos of the same under this post
please wait...Translate to English
#PuneMirajDoublingProject
● PART : PUNE TO SATARA ●
● Pune to Shindawane (31KM) FEDL
● Shindawane to Ambale (10KM)
Shindawane Ghat Doubling
Bridge no 35/1 :- Pillar work done, Span work still pending
Tunnel No 1(Dn Line) :- Boring done, Ground leveling work in progress
Bridge No 36/1 and 36/2 :- Fully done, Track Laying and Pole erection not done yet
Bridge no 37/1 :- Foundation work started
Bridge No 37/2 and 37/3 :- No Work
Bridge No 38/1 :- Pillar work done, Span work still pending
Ground Leveling almost done
Some poles are erected
Partially wiring and bracketing done from Shindawane outer to some distance
● Ambale to Wathar (78 KM) FEDL
● Wathar to Palsi (9 KM)
Ground Leveling and pole foundation work in progress
Ground leveling work yet to start at some points
● Palsi to Jarandeshwar (9 KM) FEDL
● Jarandeshwar to Satara (8 KM)
Subgrade Work, Rock Cutting work, and Minor Bridges work in progress
Blanketing ballast has arrived at some points
Total Doubled Line :- 118 KM
Under Doubling :- 27 KM
Source :- YouTube channel : KD Travel Studio
Attaching Vdos of the same under this post
● PART : PUNE TO SATARA ●
● Pune to Shindawane (31KM) FEDL
● Shindawane to Ambale (10KM)
Shindawane Ghat Doubling
Bridge no 35/1 :- Pillar work done, Span work still pending
Tunnel No 1(Dn Line) :- Boring done, Ground leveling work in progress
Bridge No 36/1 and 36/2 :- Fully done, Track Laying and Pole erection not done yet
Bridge no 37/1 :- Foundation work started
Bridge No 37/2 and 37/3 :- No Work
Bridge No 38/1 :- Pillar work done, Span work still pending
Ground Leveling almost done
Some poles are erected
Partially wiring and bracketing done from Shindawane outer to some distance
● Ambale to Wathar (78 KM) FEDL
● Wathar to Palsi (9 KM)
Ground Leveling and pole foundation work in progress
Ground leveling work yet to start at some points
● Palsi to Jarandeshwar (9 KM) FEDL
● Jarandeshwar to Satara (8 KM)
Subgrade Work, Rock Cutting work, and Minor Bridges work in progress
Blanketing ballast has arrived at some points
Total Doubled Line :- 118 KM
Under Doubling :- 27 KM
Source :- YouTube channel : KD Travel Studio
Attaching Vdos of the same under this post