🚂📢 #NewLine Updates! As part of #Tumakuru – #Davangere New Line Project
➡️Minor Bridge PCC laying completed between proposed #Anagodu and #Tolahunse Railway stations.
➡️Abutment Bed checking with situ dynamic penetration test for Road Over Bridge between proposed #Bharmasagara and #Hebbalu Railway stations
➡️Minor Bridge PCC laying completed between proposed #Anagodu and #Tolahunse Railway stations.
➡️Abutment Bed checking with situ dynamic penetration test for Road Over Bridge between proposed #Bharmasagara and #Hebbalu Railway stations
🚂📢 #NewLine Updates of construction of new board gauge line between #Tolahunse and #Bharmasagar stations (Part of #Tumakuru - #Chitadurga - #Davanagere newline project)
âś…Slope dressing work in progress
âś…Overall physical progress - 35%
âś…Targeted completion-March 2025
âś…Slope dressing work in progress
âś…Overall physical progress - 35%
âś…Targeted completion-March 2025