Electrification progress on Lalkuan - kashipur route
Lalkuan - Gularbhoj outer :- Foundation work complete, Poles erected, brackets placed and wiring not done. I’m not update with the electrification of that area because of jungle area.
Gularbhoj outer - Kashipur outer :- Foundation work complete, Poles erected, brackets placed and wiring done.
Kashipur...
more...
Electrification progress on Lalkuan - kashipur route
Lalkuan - Gularbhoj outer :- Foundation work complete, Poles erected, brackets placed and wiring not done. I’m not update with the electrification of that area because of jungle area.
Gularbhoj outer - Kashipur outer :- Foundation work complete, Poles erected, brackets placed and wiring done.
Kashipur...
more...
#Update3
Electrification from Rudarpur city has been completed on platforms and on one track of goods and on the other track the work of electrification is going on and it’s on final stage will be completed by today. After that RUPC will be fully electrified station.