Electrification progress on Lalkuan - kashipur route
Lalkuan - Gularbhoj outer :- Foundation work complete, Poles erected, brackets placed and wiring not done. I’m not update with the electrification of that area because of jungle area.
Gularbhoj outer - Kashipur outer :- Foundation work complete, Poles erected, brackets placed and wiring done.
Kashipur...
more...
Electrification progress on Lalkuan - kashipur route
Lalkuan - Gularbhoj outer :- Foundation work complete, Poles erected, brackets placed and wiring not done. I’m not update with the electrification of that area because of jungle area.
Gularbhoj outer - Kashipur outer :- Foundation work complete, Poles erected, brackets placed and wiring done.
Kashipur...
more...
#Update2
Electrification from Rudarpur city The poles have been placed in the holes and has been erected. Brackets are placed at poles but wiring are yet to be done. Same the other line of goods which is yet to be electrified in that brackets placed but wiring is left.
Electrification from Rudarpur city The poles have been placed in the holes and has been erected. Brackets are placed at poles but wiring are yet to be done. Same the other line of goods which is yet to be electrified in that brackets placed but wiring is left.