Jan 01 (18:11) Prayagraj Junction Redevelopment: ₹960 Crore Project Underway, Concourse Construction Begins
Entry# 5929479   
  Past Edits
Jan 01 2024 (18:11)
Station Tag: Prayagraj Junction (Allahabad)/PRYJ added by AdittyaaSharma^~/1421836
प्रयागराज जंक्शन पर कॉनकोर्स का निर्माण शुरू

Prayagraj Junction is undergoing a redevelopment project costing ₹960 crore. The piling work for the concourse, a crucial part of the project, has been completed and construction has begun. Platforms 9 and 10 were temporarily closed due to piling work for the 72-meter wide concourse on the Civil Lines side....
more...
Consequently, 45 trains were shifted to other platforms, causing inconvenience. Railway officials assure that the platforms will reopen soon. The structural work is scheduled to be completed by October 30, 2024, with the second phase, including the construction of a nine-story building, taking place from February 1, 2025, to December 2026. A 200-bed RPF barrack is also being built at a cost of ₹14.81 crore. The junction building will be equipped with BMS, be disability-friendly, and adhere to green building standards.

Prayagraj Junction ko ₹960 crore kharch karke renovate kiya ja raha hai. Concourse, jo ki project ka sabse important part hai, uske liye piling ka kaam khatam ho gaya hai aur ab construction start ho gaya hai. Civil Lines side pe 72 meter wide concourse banane ke liye piling ka kaam...
more...
chal raha tha, isliye platform number 9 aur 10 ko band kar diya gaya tha. Dono platforms band hone ki wajah se 45 trains ko dusre platforms pe shift kiya gaya tha, jisse dikkat badh gayi thi. Railway officials ka kehna hai ki dono platforms jaldi khul jayenge. 30 October 2024 tak structure ka main kaam complete hone ki taiyari hai. Dusra phase, jisme nine-story building banani hai, 1 February 2025 se December 2026 tak chala jayega. Junction pe ₹14.81 crore ki lagat se 200 bed wala RPF barrack bhi banaya ja raha hai. Junction ki building BMS se laas, divyang friendly, aur green building hogi.
Scroll to Top
Scroll to Bottom
Go to Desktop site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy