Today (09:17) Jabalpur Railway Station World-Class Makeover Stalled, Delays Push Project Cost Up
Entry# 6211751   
  Past Edits
This is a new feature showing past edits to this News Post.
Stations:  Jabalpur/JBP  
पीएम मोदी ने किया था शुभारंभ... सात माह बाद भी शुरू नहीं हुआ स्टेशन को वर्ल्ड क्लास बनाने का काम, यह समस्‍या आ रही

The project to transform Jabalpur Railway Station into a world-class facility has been in the works for two years, but delays due to approvals from the Railway Board and slow work from the Jabalpur Railway Division have stalled the project. The Prime Minister, Narendra Modi, virtually inaugurated the project on...
more...
February 26th, but despite the official start, the project has yet to begin construction. The initial project cost was estimated at ₹350 crores, but has since ballooned to ₹550 crores due to these delays. The Prime Minister's Office (PMO) has been notified of the stalled progress, which could lead to scrutiny from the Railway Board, West Central Railway Zone, and Jabalpur Railway Division. The project has been delayed by numerous factors, including disagreements between the previous contractor and the railway division over payments and commissions, and changes to the design plans. The Jabalpur Railway Division has taken more than a year to finalize the design plans, and the responsibility for the increasing project cost remains unclear. A new contractor is being considered, and the division aims to release the tender by November 30th, but given the delays so far, it is unlikely this deadline will be met. The delay in initiating the project has raised questions about the lack of preparation before the Prime Minister's launch event.

Jabalpur Railway Station ko world-class banane ka project do saal se chal raha hai, lekin Railway Board se approval aane mein der aur Jabalpur Railway Division ki slow work ki wajah se ab tak kaam start nahin hua. PM Narendra Modi ne 26 February ko virtual launch kiya tha, lekin...
more...
saath mahine baad bhi kaam nahin chala. Project ki cost ₹350 crore se badhkar ₹550 crore ho gayi hai. PMO ko shikayat aane se Railway Board, West Central Railway Zone aur Jabalpur Railway Division pe pressure badh sakta hai. Pehle contractor aur railway division ke beech payment aur commission ko leke disagreement aur design plan mein changes ki wajah se bhi der ho rahi hai. Jabalpur Railway Division ko design finalize karne mein ek se dedh saal lag gaya, aur cost badhne ke liye zimmedar koi nahin hai. Naya contractor dhundha ja raha hai, aur tender 30 November tak release hone ka plan hai, lekin pehle ki delays ko dekhte hue yeh deadline bhi nahin mil payega. Project launch se pehle proper planning nahin hone ka sawaal uth raha hai.
Scroll to Top
Scroll to Bottom
Go to Desktop site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy