Feb 26 2019 (22:58) Aur doubling hu rehe h waha waha 80% electfication hu gaya h haripura to marwar outer 100% hu gaya h Complete appox 257 km
Feb 26 2019 (22:55) Station Tag: Mahesana Junction/MSH added by Sandeeptanwar1409~/1938326
Feb 26 2019 (22:55) Station Tag: Ahmedabad Junction/ADI added by Sandeeptanwar1409~/1938326
Feb 26 2019 (22:55) Station Tag: Abu Road/ABR added by Sandeeptanwar1409~/1938326
Feb 26 2019 (22:55) Station Tag: Marwar Junction/MJ added by Sandeeptanwar1409~/1938326
Feb 26 2019 (22:55) Station Tag: Phulera Junction/FL added by Sandeeptanwar1409~/1938326
Feb 26 2019 (22:55) Station Tag: Ringas Junction/RGS added by Sandeeptanwar1409~/1938326
Feb 26 2019 (22:55) Station Tag: Jaipur Junction/JP added by Sandeeptanwar1409~/1938326
Feb 26 2019 (22:55) Station Tag: Ajmer Junction/AII added by Sandeeptanwar1409~/1938326
Ajmer ko palanpur #doubling update 357km Incomplete in detail Ajmer to durai gound levelling going on Durai to magaliyawas almost complete 90% Bangurgram halt to bewar 60% work done Bewar... more...
to haripura 15% only done its takes min one year briges work going on Aur doubling hu rehe h waha waha 80% #electfication hu gaya h haripura to marwar outer 100% hu gaya h On progress 1. Ajmer to magaliyawas 26km 2. Bangurgram halt to haripur 38km 3. Maval to bhimana 27 km 4. Kajoda to jatni 10 km Appox in progress 100km Complete 1. Palanpur to kajoda 7 km 2. Jatni to maval 27km 3. Bhimana to haripur 203km 4. Bangurgram to magaliyawas 27km Complete appox 257 km
Feb 12 2019 (18:12) Bandikui to Gandhi nagar poles 90% wiring 0% poles till jaipur outer After all complete work jp is biggest Railway Station in rajasthan in teams of pf haveing 9 pf
Feb 12 2019 (18:11) After all complete work jp is biggest Railway Station in rajasthan in teams of pf haveing 9 pf
Feb 12 2019 (18:10) Bki to bti bte elecfication After all complete work jp is biggest Railway Station in teams of pf haveing 9 pf
Feb 12 2019 (18:09) Station Tag: Phulera Junction/FL added by Sandeeptanwar1409~/1938326
Feb 12 2019 (18:09) Station Tag: Ajmer Junction/AII added by Sandeeptanwar1409~/1938326
Feb 12 2019 (18:09) Station Tag: Sikar Junction/SIKR added by Sandeeptanwar1409~/1938326
Feb 12 2019 (18:09) Station Tag: Ajmer Junction/AII added by Sandeeptanwar1409~/1938326
Feb 12 2019 (18:09) Station Tag: Alwar Junction/AWR added by Sandeeptanwar1409~/1938326
Feb 12 2019 (18:09) Station Tag: Rewari Junction/RE added by Sandeeptanwar1409~/1938326
Feb 12 2019 (18:09) Station Tag: Bharatpur Junction/BTE added by Sandeeptanwar1409~/1938326
Feb 12 2019 (18:09) Station Tag: Bandikui Junction/BKI added by Sandeeptanwar1409~/1938326
Jaipur devision all project update 1. Delhi jaipur eleticification Delhi alwar complete Alwar bandikui single line elecfication on progress Poles 95% wireing... more...
0% No work on bandikui railway station Bandikui to Gandhi nagar poles 90% wiring 0% poles till jaipur outer Digging work complete on Gandhi nagar no. Poles No work on jaipur railway station 2. Alwar bandikui doubling Alwar dhigawana complete Dhigawana to bandikui 0% track laying but all brige are complete 3. Bki to bte elecfication Poles 90% wiring 0% 4. Jaipur to ringas gc Jaipur railway station new pf 70% work done Track linking pending. Jaipur to govindgarh 75% work done track linking pending. Govindgarh to ringas 60% work done track linking and ringas brige pending 5. Swm jp elecfication. Poles 90% Wiring 10% 6. Ajmer jaipur elecfication Jaipur to phulera poles 70% wireing 0% Phulera to mader jn poles 95% wireing 25% No elecfication work on bandikui, new pf of alwar, jaipur railway station and ajmer railway station After all complete work jp is biggest Railway Station in rajasthan in teams of pf haveing 9 pf
Important Note:This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks. Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.