Jun 08 2014 (2:30PM) Power and Traffic Block for 6 days for pre-non -interlocking work for commissioning of double line between Kalinarayanpur and Phulia frm 9/6/14-17/6/14
Jun 08 2014 (2:29PM) Power and Traffic Block for 6 days for pre-non -interlocking work for commissioning of double line between Kalinarayanpur and Phulia frm 9/6/14-17/6/14
Jun 08 2014 (2:29PM) Train Tag: Shantipur-Sealdah Local/31512 added by Vaibhav Agarwal*^/432532 Station Tag: Phulia/FLU added by Vaibhav Agarwal*^/432532
Power and Traffic Block for 6 days for pre-non -interlocking work for commissioning of double line between Kalinarayanpur and Phulia frm 9/6/14-17/6/14
Jan 09 2014 (9:41PM) Power and Traffic Block for 10 days from 10/11 - 22/23 January between Kalinarayanpur and Shantipur for pre non interlocking work for commisioning of double line between Phulia and Shantipur
Jan 09 2014 (9:40PM) Station Tag: Kalinarayanpur Junction/KLNP added by Vaibhav Agarwal*^/432532
Jan 09 2014 (9:40PM) Train Tag: Shantipur-Sealdah Local/31512 added by Vaibhav Agarwal*^/432532
Power and Traffic Block for 10 days from 10/11 - 22/23 January between Kalinarayanpur and Shantipur for pre non interlocking work for commisioning of double line between Phulia and Shantipur
Dec 25 2013 (1:38PM) Traffic Block between Shantipur and Kalinarayanpur on 25/26 , 27/28 December For machine packing and unloading of ballast for raising speed on newly commissioned line between Shantipur and Phulia
Dec 25 2013 (1:37PM) Station Tag: Kalinarayanpur Junction/KLNP added by Vaibhav Agarwal**/432532
Dec 25 2013 (1:37PM) Train Tag: Shantipur-Sealdah Local/31512 added by Vaibhav Agarwal**/432532
Traffic Block between Shantipur and Kalinarayanpur on 25/26 , 27/28 December For machine packing and unloading of ballast for raising speed on newly commissioned line between Shantipur and Phulia
Dec 20 2013 (12:52PM) Train Tag: Shantipur-Sealdah Local/31512 added by Vaibhav Agarwal**/432532 Station Tag: Kalinarayanpur Junction/KLNP added by Vaibhav Agarwal**/432532
Traffic Block Between Kalinarayanpur and Shantipur stations over Sealdah Division on 20/12/13 and 21/12/13 leading to short-termination and short-origination of trains
Important Note:This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks. Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.