Dec 24 2022 (19:17) Just CRS After inspection Chabbra, done LC on post 13 wasremovedsotracklayingworkispendinginverylittlepart Further, 12 Trackisready,OHEwiresarestretchedexceptforapartoflessthan500mwhereonlycantileversareinstalled Kesholi 2022 Station:TracklayingworkfornewPFisunderprogress&PFworkwilltakemoretime From CRS Kesholi inspection towards done Salpura, on connection 13 oflooplinetomainlineismissing,tracksneedtobelayed 12 further 2022 trackof2-3kmisReady,OHEpolesareerectedwithcantilevers afterthatonlytrackbedisreadyforAndheriRiverbridge+threeminorbridge+lahasiriverBridge NoworkhasbeenstartedfornewPFatSalpura loco trial has been done & Interlocking NI Block is pending scheduled from 25 12 2022 till 05 01 2023 this expected is to only be part commissioned which by is January untouched (most till probably date by end of thus FY) Butoncestarteditwon'ttakemuchtimeastheycouldrevivetwooldlooplineswhicharenotinuse,bychangingtheiralignment OHE poles are visible on this blank section (without track) with cantilevers installed till Kota Junction
Dec 03 2022 (06:48) MotiPura Chauki - Bhulon : CRS Inspection done on 30 Track 06 isready,OHEwiresareinstalled Bhulon 2022 station:Demolitionofoldbuildingunderprocess,newbuildingisreadytoserve,CivilworkofPFispending&constructionofFOBisstarted Bhulon - Chhabra Gugor : CRS Inspection done on 30 Track 06 isready,OHEwiresareinstalled Chhabra 2022 Gugorstation:PFalmostready,onlyminorworkispending&OHEwireneedtobeinstalledatnewPF loco trial has been done & Interlocking is pending But once started it won't take much time as they could revive two old loop lines which are not used in use, by changing their alignment Bina Mahadeokhedi - Malkhedi Doubling : CRS Inspection done on 18 This 11 isreadytobeinspectedbyCRS 2022
May 19 2022 (08:41) Station Tag: Guna Junction/GUNA added by RamganjMandi/720659
May 19 2022 (08:41) Station Tag: Bina Junction/BINA added by RamganjMandi/720659
May 18 2022 (06:52) Kota - Ruthiyai Bina Doubling Progress MotiPura A Chauki-Bhulon Sogaria - Ruthiyai Section 1 MotiPura Chauki - Bhulon Bhulon 2 -ChhabraGugor Bhulon - Chhabra Gugor Chhabra 3 Gugor-Kesholi Chhabra Gugor - Kesholi Kesholi 4 -Salpura Kesholi - Salpura B Guna - Bina only left section was Kanjiya - Pipraigaon, which is now ready to be inspected by CRS loco trial has been done C Sogaria - Kota this is only part which is untouched till date But once started it won't take much time as they could revive two old loop lines which are not used by changing their alignment OHE poles are visible on this blank section (without track) with cantilevers installed till Kota Junction
May be this is delayed because of wagon repair shop's yard Bina Mahadeokhedi - Malkhedi Doubling This is ready to be inspected by CRS
May 17 2022 (23:38) Kota - Ruthiyai Doubling Progress No work has been started for new PF at Salpura
May 17 2022 (23:38) Station Tag: Salpura/SYL added by RamganjMandi/720659
May 17 2022 (23:38) Station Tag: Kesholi/KOLI added by RamganjMandi/720659
May 17 2022 (23:38) Station Tag: Motipura Chauki/MTPC added by RamganjMandi/720659
May 17 2022 (23:38) Station Tag: Bhulon/BLO added by RamganjMandi/720659
May 17 2022 (23:38) Station Tag: Chhabra Gugor/CAG added by RamganjMandi/720659
A. Sogaria - Ruthiyai Section 1. MotiPura Chauki - Bhulon : CRS Inspection done on 30.06.2022 2. Bhulon - Chhabra Gugor : CRS Inspection done on 30.06.2022 3.... more...
Chhabra Gugor - Kesholi CRS inspection done on 13.12.2022 4. Kesholi - Salpura CRS inspection done on 13.12.2022
B. Guna - Bina only left section was Kanjiya - Pipraigaon, which is now ready to be inspected by CRS. loco trial has been done & NI Block is scheduled from 25.12.2022 till 05.01.2023.
C. Sogaria - Kota expected to be commissioned by January (most probably by end of thus FY)
Bina Mahadeokhedi - Malkhedi : CRS Inspection done on 18.11.2022
Important Note:This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks. Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.