#update16The final update of Moradabad - Ramnagar route electrificationSpeed trail and the electrification work inspected today on 29/11/2022. Now this full route has been electrified from today.
×
75656 views
0
@KGFR 1h 16m late@KGF: Kathghar &84 km/h
×
74917 views
0
@KGF 1h 17m late@KGF: Kathghar &58 km/h
×
KPV/Kashipur Junction
79705 views
1
#update9Electrification progress on Moradabad - kashipur - Ramnagar routeMoradabad - Got outer :- Electrification is complete.Got outer - Kashipur outer :- Foundation work complete, Poles erected, brackets placed and wiring not done.Kashipur :- Foundation work complete, Poles erected, brackets placed and wiring not done.Kashipur outer - Ramnagar outer:- Foundation work complete, Poles erected, brackets placed and wiring not done.Ramnagar :- Foundation work complete, Poles erected, brackets placed and wiring not done.This is the progress of electrification on Moradabad - Ramnagar route.SSP details:-Pipalsana SSP will completed Roshanpur SSP completed.Kashipur SSP work has not started.Ramnagar SSP work has not started.Note :-Wring will start...
×
KPV/Kashipur Junction
79705 views
1
#update9Electrification progress on Moradabad - kashipur - Ramnagar routeMoradabad - Got outer :- Electrification is complete.Got outer - Kashipur outer :- Foundation work complete, Poles erected, brackets placed and wiring not done.Kashipur :- Foundation work complete, Poles erected, brackets placed and wiring not done.Kashipur outer - Ramnagar outer:- Foundation work complete, Poles erected, brackets placed and wiring not done.Ramnagar :- Foundation work complete, Poles erected, brackets placed and wiring not done.This is the progress of electrification on Moradabad - Ramnagar route.SSP details:-Pipalsana SSP will completed Roshanpur SSP completed.Kashipur SSP work has not started.Ramnagar SSP work has not started.Note :-Wring will start...
×
KPV/Kashipur Junction
79705 views
1
#update9Electrification progress on Moradabad - kashipur - Ramnagar routeMoradabad - Got outer :- Electrification is complete.Got outer - Kashipur outer :- Foundation work complete, Poles erected, brackets placed and wiring not done.Kashipur :- Foundation work complete, Poles erected, brackets placed and wiring not done.Kashipur outer - Ramnagar outer:- Foundation work complete, Poles erected, brackets placed and wiring not done.Ramnagar :- Foundation work complete, Poles erected, brackets placed and wiring not done.This is the progress of electrification on Moradabad - Ramnagar route.SSP details:-Pipalsana SSP will completed Roshanpur SSP completed.Kashipur SSP work has not started.Ramnagar SSP work has not started.Note :-Wring will start...
×
KPV/Kashipur Junction
79705 views
1
#update9Electrification progress on Moradabad - kashipur - Ramnagar routeMoradabad - Got outer :- Electrification is complete.Got outer - Kashipur outer :- Foundation work complete, Poles erected, brackets placed and wiring not done.Kashipur :- Foundation work complete, Poles erected, brackets placed and wiring not done.Kashipur outer - Ramnagar outer:- Foundation work complete, Poles erected, brackets placed and wiring not done.Ramnagar :- Foundation work complete, Poles erected, brackets placed and wiring not done.This is the progress of electrification on Moradabad - Ramnagar route.SSP details:-Pipalsana SSP will completed Roshanpur SSP completed.Kashipur SSP work has not started.Ramnagar SSP work has not started.Note :-Wring will start...
×
KPV/Kashipur Junction
79705 views
1
#update9Electrification progress on Moradabad - kashipur - Ramnagar routeMoradabad - Got outer :- Electrification is complete.Got outer - Kashipur outer :- Foundation work complete, Poles erected, brackets placed and wiring not done.Kashipur :- Foundation work complete, Poles erected, brackets placed and wiring not done.Kashipur outer - Ramnagar outer:- Foundation work complete, Poles erected, brackets placed and wiring not done.Ramnagar :- Foundation work complete, Poles erected, brackets placed and wiring not done.This is the progress of electrification on Moradabad - Ramnagar route.SSP details:-Pipalsana SSP will completed Roshanpur SSP completed.Kashipur SSP work has not started.Ramnagar SSP work has not started.Note :-Wring will start...
Important Note:This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks. Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.