Jun 29 2016 (14:50) SBC/KSR Bengaluru City Junction (Bangalore) (10 PFs)
krishnaprasad~
krishnaprasad~ 3086 blog postsSir, do u know the progress of MYS-RMGM electrification ??
Hope to see SBC-RMGM MEMU from Aug 1st.
Hope to see SBC-RMGM MEMU from Aug 1st.
Sir I am asking about MYSURU-RMGM . I think u r mistaking me that I am asking about SBC-RMGM.
it has reached upto MNGT from RMGM. RMGM to MYA - COMPLETE
MYA station elec'ficatn is going on
MYA-Y completed
Y - almost done
Y - BDRL completed
BDRL...
more...
MYA station elec'ficatn is going on
MYA-Y completed
Y - almost done
Y - BDRL completed
BDRL...
more...