Feb 16 2015 (12:30) GR/Kalaburagi Junction (Gulbarga) (4 PFs)
![](http://st.indiarailinfo.com/images/1.png)
SunilKulkarni~
SunilKulkarni~ 2006 blog postsBidar Gulbarga Line updates
--Almost tracks from Gulbarga station till Kamalapur is layed with some gaps in between for ROB/RUB and minor bridges...
--- Bennethora Bridge near Kurikota is completed only tracks needs to be layed
--- By this month end Engine will roll from Gulbarga station till kilometer 21 which will pass Bennethora bridge also and reach mahagoan
---...
more...
--Almost tracks from Gulbarga station till Kamalapur is layed with some gaps in between for ROB/RUB and minor bridges...
--- Bennethora Bridge near Kurikota is completed only tracks needs to be layed
--- By this month end Engine will roll from Gulbarga station till kilometer 21 which will pass Bennethora bridge also and reach mahagoan
---...
more...
3 Public Posts - Mon Feb 16, 2015
Pit line construction is such delay...then how worst will the worker be allocated and how much it be delayed in fitting suitable machinery and go for live :(
CR should have done some alternative for GR-HYB ICE
They should have run SUR-GR exp and GR-HYB exp with RSA
CR should have done some alternative for GR-HYB ICE
They should have run SUR-GR exp and GR-HYB exp with RSA
3 Public Posts - Mon Feb 16, 2015
1 Public Posts - Tue Feb 17, 2015