उदयपुर-अहमदाबाद लाइन का आमान परिवर्तन mg to bg के बारे में जानकारी अपडेट करना
Himmatnagar-Udaipur (208.48 km)-
Earthwork done during the month – 33,000 cum, cumulative progress – 29,34,000 cum out of total 71,00,000 cum.
Minor bridges completed during the month 03 nos., cumulative progress - 223 nos. out of total 636 nos.
Major bridges completed during the month 01 no., cumulative progress - 14 nos. out of total 45 nos.