Apr 26 2017 (14:27) SUBL/Hubballi South (Hubli) (1 PFs)
SingleTraveller^~
SingleTraveller^~ 3276 blog postsIn this post I will update the progress of doubling of Hubballi-Chikjajur and Arsikere-Tumakuru sections.
-
In this first post are pics from Hubballi South to Savanur stations and also of doubling progress. The pics are in the order from SUBL to SVNR.......
- Land levelling has been done at many places, is on at some places.
-...
more...
-
In this first post are pics from Hubballi South to Savanur stations and also of doubling progress. The pics are in the order from SUBL to SVNR.......
- Land levelling has been done at many places, is on at some places.
-...
more...
1 Posts
Savanur to Chikjajur. The pics are in the same order too......
-
Between Mayakonda-Sasalu-Chikjajur track laying is completed at some places. Ballast packing is left and of course signal and interlocking too. Steady progress is on.......
-
More...
more...
-
Between Mayakonda-Sasalu-Chikjajur track laying is completed at some places. Ballast packing is left and of course signal and interlocking too. Steady progress is on.......
-
More...
more...
Chikjajur to Arsikere. The pics are in same order.
-
This section is doubled but many places RuB work is on, some places where pre-cast sections were used for creating RuBs.
-
- JRU...
more...
-
This section is doubled but many places RuB work is on, some places where pre-cast sections were used for creating RuBs.
-
- JRU...
more...
Arsikere-Tumakuru.
-
Here is the best part. The work on this section (most needed to reduce congestion) is going on at a fast pace. Between ASK and TTR tracks have been laid at many places and other work along the section like bridge construction is on at night too. Since it was dark, not many pics could be taken. At TK, 4th PF is completed.
-
Here is the best part. The work on this section (most needed to reduce congestion) is going on at a fast pace. Between ASK and TTR tracks have been laid at many places and other work along the section like bridge construction is on at night too. Since it was dark, not many pics could be taken. At TK, 4th PF is completed.
Thanks very much for the updates. Any idea if the tracks will be LWR or CWR? If it's CWR, I hope 130km/h mps can be granted for current and possible future LHB trains (YPR-JP suvidha, TPJ HS).