New Railway Electrification Contract Finalised
1.Manikpur (excl) --Satna (incl) and Satna to Rewa Total 127RKM and 309 TKM (Awarded to M/s SKS-CEC, Agra) Date of Completion 24 Months
Value of contract -66 Crores
2. Bandikui- Bharatpur Total 97 RKM/116 TKM (Awarded to M/s KEC International, Gururgram) Date of Completion 18 Months.
Value...
more...
1.Manikpur (excl) --Satna (incl) and Satna to Rewa Total 127RKM and 309 TKM (Awarded to M/s SKS-CEC, Agra) Date of Completion 24 Months
Value of contract -66 Crores
2. Bandikui- Bharatpur Total 97 RKM/116 TKM (Awarded to M/s KEC International, Gururgram) Date of Completion 18 Months.
Value...
more...
Iska matlab......Manikpur-Satna-Rewa section me kaam suru nehi hua he !!