wahi to problem hai ki Oct 2009 me clearance milne ke baad tender allot hone me hi 5 saal ho gaya. 2014 se jo kaam shuru hua hai .
uske baad fir 2 saal me 17 km complete hoke feb 16 me gudum tak pahucha . abhi 3 saal me bhanupratap pur aa ya hai jo ki situtaion ko dekhte hue satisfactory hai.
main delay 2009 se 14 ke hi beech hi hua hai