#ShiradiGhat
Located at 889 m above MSL, this is where the ghat section begins. It took 2 Hrs 45 mins to climb down 55 Kms. It has 57 tunnels in the span of some 45 Kms. Finally climbing down to 114 m.
Ticket is inflated by 55 Kms.
.
From...
more...
Located at 889 m above MSL, this is where the ghat section begins. It took 2 Hrs 45 mins to climb down 55 Kms. It has 57 tunnels in the span of some 45 Kms. Finally climbing down to 114 m.
Ticket is inflated by 55 Kms.
.
From...
more...
12 Posts
Only OHE Foundation work completed at Kumta a month ago. OHE foundation work going on at between Block stations.
As per information , Poles have been laid in between Murudeshwar & Bhatkal stations & Padubidri station in Karnataka Part of KR. Work is going simultaneously everywhere & very fast as compared to rest of IR.
Last 2 Sundays, they had took Block for laying poles at above mentioned locations.
As per information , Poles have been laid in between Murudeshwar & Bhatkal stations & Padubidri station in Karnataka Part of KR. Work is going simultaneously everywhere & very fast as compared to rest of IR.
Last 2 Sundays, they had took Block for laying poles at above mentioned locations.
Block for pole laying?
So they are using equipments train for the transportation of poles rather than the usual 'dump at side' and then carry it to the site and fix.
So they are using equipments train for the transportation of poles rather than the usual 'dump at side' and then carry it to the site and fix.
Yes. Poles are carried on Flat bed wagons along with Crane to lift & place them.
Also Block includes other works in different sections like preparation of OHE Foundation. For that The Cement Mixer, Materials, DG, etc are all carried on Flat bed wagons for working in Block sections.
Also Block includes other works in different sections like preparation of OHE Foundation. For that The Cement Mixer, Materials, DG, etc are all carried on Flat bed wagons for working in Block sections.
/blog/post/3819122
Refer above Blog entry for Cement mixer train found at Barkur, by MAQ based Admin Titus.
Refer above Blog entry for Cement mixer train found at Barkur, by MAQ based Admin Titus.