Mar 25 2019 (19:50) 16352/Nagercoil - Mumbai CSMT Express (via Renigunta) (PT) | KWV/Kurduwadi Junction (4 PFs)
psanga_sur^~
psanga_sur^~ 5601 blog posts#PuneSolapurDoubling
While traveling in 16352 Nagarcoil - Tirupati - Mumbai Express, I have observed following progress of doubling.
Wadshinge - Interlocking work for UP main line is already completed new signals are ready for functioning.
Kurduwadi - Wadshinge to Kurduwadi outer track laid long back. Now the progress is KWV outer to KWV Junction new tracks are laid.
Major...
more...
While traveling in 16352 Nagarcoil - Tirupati - Mumbai Express, I have observed following progress of doubling.
Wadshinge - Interlocking work for UP main line is already completed new signals are ready for functioning.
Kurduwadi - Wadshinge to Kurduwadi outer track laid long back. Now the progress is KWV outer to KWV Junction new tracks are laid.
Major...
more...
28 Posts
RB rejected SUR Division proposal of block for interlocking as RUB at KWV is not ready.
/blog/post/4349878
/blog/post/4349878
see Dhananja Hunasgi’s latest doubling status video then it seems there is no much work done, from Bhigwan to Washimbe still incomplete leveling work is seen, same as six month old video...
Pune miraj started last year only but it seems they are well ahead, electrification also started, bhigwan mohol doubling will take another 5 years to complete doubling and further 5 years for electrification.
“Jab RG PM banega tabhi bhigwan mohol doubling complete hoga” LOL
“Jab RG PM banega tabhi bhigwan mohol doubling complete hoga” LOL