Blog Entry# 4286936
Posted: Apr 10 2019 (19:09)

1 Responses
Last Response: Apr 11 2019 (11:19)
Info Update
51418 views
2

Apr 10 2019 (19:09)   KIR/Katihar Junction (9 PFs)
Rkj_78^~
Rkj_78^~   11956 blog posts
Entry# 4286936            Tags   Past Edits
Engineering Department of N.F. Railway has been able to raise the speed of 14 sections covering a length of 736 kms. during the financial year 2018-19. This raising of speed has led to saving of 133.47 minutes. Some important sections where the speed has been raised are as follows:
SN Name of Section Length Speed raised
(Track Km) From Kmph To Kmph
===
1
...
more...
Katihar - Kumedpur 30.00 100 110
2 Katihar - Radhikapur 53.60 100 110
3 Aluabari - Siliguri 76.00 90 100
4 Fakiragram 46.99 50 75
5 North Lakhimpur-Sripani 81.46 80 100
6 Sripani - Murkongselek 72.32 75 100
===
It is to be mentioned that trains are allowed to run over designated sections of railway track with certain permissible speed, when the permissible speed of a particular track section is raised by suitable inputs to strengthen the track structure, the trains are allowed to run at a higher speed. This result in decreasing the travel time of the trains and the net saving of time required to travel over these sections. The Engineering Department has been able to provide systematic inputs to the track which has made the achievement possible.
To this end N.F. Railway has been able to carry out a track renewal of 104 CTR units which is higher than the target stipulated by Railway Board. Almost 7.32 km of track has been deep screened by using mechanized screening arrangements while through fitting renewal has been done over a length of 402 km. In this connection as many as 4334 numbers of bridge sleepers have also been replaced by new sleepers in important bridges all over the zone. For greater safety of track, the zone has also resorted to flash butt welding of rail joints making a cumulative progress of almost 35,000 joints during the fiscal. Flash butt welding is a superior technology of welding which gives jerk free and safe welding of rails. It is also to be mentioned that in as many as 19 stations the permissible speeds in the platform lines have been raised from 15 kmph to 30 kmph leading to the saving of 57 minutes.
===
source -NFR official fb page.

Translate to English
Translate to Hindi

24913 views
1

Apr 11 2019 (11:19)
mazhar.nfr~
mazhar.nfr~   1892 blog posts
Re# 4286936-3              
good news
Translate to English
Translate to Hindi
Scroll to Top
Scroll to Bottom
Go to Desktop site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy