At last SECR has said that work between NIR-Samnapur will complete within 31 June 2019 so hopefully in July CRS will b invited for inspection of NIR-Samnapur section and may b by Aug 2019 we can see new trains on this section so hope for the best
#NIRSAMNAPURBGUPDATES
#JBPGBGPROJECTUPDATES
At last SECR has said that work between NIR-Samnapur will complete within 31 June 2019 so hopefully in July CRS will b invited for inspection of NIR-Samnapur section and may b by Aug 2019 we can see new trains on this section so hope for the best
4 Public Posts - Mon Apr 22, 2019
2 Public Posts - Fri May 17, 2019
According to RailPost Bureau dated on 15/04/2019, details of the spillover works on SECR from the previous financial year, and their new timelines for completion are
1. Section- Nainpur-Lamta , Total Length-36 KM will expected to commissioned on June 2019. The rest Lamta-Samnapur section having length 25 KM will expected to commissioned on October 2019.
2. Section- Chiraidongri -Mandla Fort, Total Length-24 KM will expected to commissioned on October 2019.
3....
more...
1. Section- Nainpur-Lamta , Total Length-36 KM will expected to commissioned on June 2019. The rest Lamta-Samnapur section having length 25 KM will expected to commissioned on October 2019.
2. Section- Chiraidongri -Mandla Fort, Total Length-24 KM will expected to commissioned on October 2019.
3....
more...