जबलपुर, नईदुनिया प्रतिनिधि।
जबलपुर...
जबलपुर...
read more... 22 साल में भी पूरी नहीं हो सकी ब्रॉडगेज लाइन
Absolutely rubbish and the fake news. What the hell the press editor wrote on the news-paper. I think they didn't know the all routes of new formed broad gauge line. First of all, Charidongri station meet at Mandla fort terminus way and yet the conversion of broad gauge line ended at charidongri station. From Nainpur to samnapur (which is the other route) there are two main station and they are Padriganj and Lamta. Yet there is no information of completion of track route from nainpur to samnapur. Please, may provide a right information to us, my dear Newspaper wala.
According to RailPost Bureau dated on 15/04/2019, details of the spillover works on SECR from the previous financial year, and their new timelines for completion are
1. Section- Nainpur-Lamta , Total Length-36 KM will expected to commissioned on June 2019. The rest Lamta-Samnapur section having length 25 KM will expected to commissioned on October 2019.
2. Section- Chiraidongri -Mandla Fort, Total Length-24 KM will expected to commissioned on October 2019.
3....
more...
1. Section- Nainpur-Lamta , Total Length-36 KM will expected to commissioned on June 2019. The rest Lamta-Samnapur section having length 25 KM will expected to commissioned on October 2019.
2. Section- Chiraidongri -Mandla Fort, Total Length-24 KM will expected to commissioned on October 2019.
3....