Latest Updates on ADI VG RE as spotted by me today:- Only Chharodi station and VG Jn remain to be wired. Horizontal masts have been placed from Pf no. 1 to 3 on VG Jn meaning that RJT ADI Main Line would be electrified first. The VG yard towards SUNR end has Horizontal masts placed too. Won't take long for VG to be electrified. After VG, zero progress has been observed! #Electrification #ADIRJTRE
Every loop line has been wired on the ADI VG stretch. Hoping that ANND ADI MEMU will be extended to VG by August.
if MEMU gets extended ,than it would be more convinient for passengers