ELECTRIFICATION UPDATE DECEMBER 2019
*Madgaon-Kumta-Bhatkal section*
*Madgaon-Harwada* - Foundation work started at Balli
*Harwada* - Foundation work complete on PF and outer
*Harwada-Ankola* - No work
...
more...
*Madgaon-Kumta-Bhatkal section*
*Madgaon-Harwada* - Foundation work started at Balli
*Harwada* - Foundation work complete on PF and outer
*Harwada-Ankola* - No work
...
more...
What about Madgaon Traction sub station. Transformers are arrived at MAO left side near running room Can anyone get the update are they for TSS or any other
What is the status of in progress work of MAO - MJO Automatic Block Signal System
( MAO - QLM Doubling )
SWR also started track doubling Work from MAO yard left Side below ROB UBL end and 1 Track Right of 1st Pitline PNVL end I think it will be Stabling line for parking KR Trains. Full speed Ground level work in Progress and Deadline to complete is 30th April 2020.
SWR also started track doubling Work from MAO yard left Side below ROB UBL end and 1 Track Right of 1st Pitline PNVL end I think it will be Stabling line for parking KR Trains. Full speed Ground level work in Progress and Deadline to complete is 30th April 2020.