ELECTRIFICATION UPDATE DECEMBER 2019
*Madgaon-Kumta-Bhatkal section*
*Madgaon-Harwada* - Foundation work started at Balli
*Harwada* - Foundation work complete on PF and outer
*Harwada-Ankola* - No work
...
more...
*Madgaon-Kumta-Bhatkal section*
*Madgaon-Harwada* - Foundation work started at Balli
*Harwada* - Foundation work complete on PF and outer
*Harwada-Ankola* - No work
...
more...
2 Public Posts - Tue Dec 24, 2019
( MAO - QLM Doubling )
SWR also started track doubling Work from MAO yard left Side below ROB UBL end and 1 Track Right of 1st Pitline PNVL end I think it will be Stabling line for parking KR Trains. Full speed Ground level work in Progress and Deadline to complete is 30th April 2020.
SWR also started track doubling Work from MAO yard left Side below ROB UBL end and 1 Track Right of 1st Pitline PNVL end I think it will be Stabling line for parking KR Trains. Full speed Ground level work in Progress and Deadline to complete is 30th April 2020.